"Port of Portland readies three proposals for Hillsboro, Ore., airport expansion"


 
Friday, December 3, 2004

Port of Portland readies three proposals for Hillsboro, Ore., airport
expansion
The Oregonian 


Portland, Ore. -- By 2025, Hillsboro Airport's parking lot could include as
much as one-fourth of the Washington County Fair Complex, and expected
growth in flights and aircraft could require a costly move of Northwest
Cornell Road. 

The Port of Portland, the airport's operator, has crafted three packages to
prepare for increasing demand. Those alternatives -- which could include
turning about 25 acres of nearby fairgrounds into parking space and moving
Northwest Evergreen Road again -- were reviewed by the master plan committee
Thursday night. 

The committee, consisting of airport operators and users, business owners
and community members, told Port officials they don't want Evergreen Road to
be moved and would like to seek county approval before signing off on the
relocation of Cornell Road. 

If approved, the changes would become part of the airport's master plan, a
blueprint that will address airport demand and community concerns for the
next 20 years. The Port and committee have been working for a year to update
the plan and expect to complete it in the spring. 

The upgrades would be phased in over time as demand increases and would
depend on whether the Port can find money, which would generally come from a
series of Port and Federal Aviation Administration grants. By 2025, Port
officials expect the number of aircraft based at Hillsboro Airport, Oregon's
second-largest airport, to increase from 363 to 465. The number of takeoffs
and landings is expected to rise from 224,000 in 2003 to 323,000. 

During the past year, the committee has gathered to review the nuts and
bolts of the airport, including its role, inventory, demand and capacity. 

On Thursday, after an open house Wednesday, the Port unveiled three
development packages, ranging from $52.9 million to $126 million. All three
options, which take into account land and air demands, call for a series of
upgrades, including a new runway spanning 3,600 feet. That runway, which
Port officials have wanted to build for more than a decade, would be built
on the north end of the airport parallel to the existing 6,600-foot runway
and perpendicular to another existing 4,049-foot runway. It would be used
solely for landing small-engine aircraft. 

That would allow larger business jets to land more quickly on the longest
runway, said Daren Griffin, general aviation manager for the Port of
Portland. 

"We would spend less time circling in the pattern, wasting gas and creating
noise," Griffin said. With each alternative, noise levels -- which will be
addressed by the Port in the coming months along with environmental concerns
-- will spread out over a larger area. 

The noise, however, will still remain within airport property, Griffin said.


In addition to a third runway, all three packages call for a series of new
taxiways, about 367,950 square feet more of hangar space, relocation of the
terminal and more parking for cars and aircraft. 

Alternative A, costing about $52.9 million, proposes the fewest changes,
adding a new runway and several taxiways and hangars.

Alternative B, which would cost about $90.8 million, would include moving
Northwest Cornell Road -- which currently runs along the airport's southern
edge -- about 400 feet south and acquiring about 25 acres of fairgrounds
land -- currently across Cornell -- to make space for car and aircraft
parking, along with business buildings. 

It also would include shifting the smaller runway about 235 feet toward the
east and relocating the terminal closer to the MAX light-rail station, which
is next to Northwest 34th Avenue and Cornell. 

Alternative C, which would cost between $101.4 million and $126 million,
includes two options. One consists of buying about 90 acres of mostly
agricultural and industrial land north of the airport to build a new flight
pattern known as Charlie -- the existing Charlie pattern has been active for
about a month and is located parallel to the 6,600-foot runway, close to
where the new runway would be built. 

To keep up with an expected increase in flights and to segregate helicopter
flights, a new Charlie pattern would need to be built on the northeast end
of the airport, Griffin said. 

If so, that would mean more noise along that end of the airport, Griffin
said.

Henry Oberhelman, who lives along the airport's north edge, worries that may
mean more disruption for him. 

"We're going to be right below the flight area," said Oberhelman, who is a
member of the Washington County Residents for Safe & Quiet Skies and
Concerned Residents Against Student Helicopters, a group lobbying against
helicopter noise at the airport. Oberhelman also worries about the impact
airport growth will have on small business in the area. 

Wink Brooks, a city planning director who sits on the master plan committee
representing Hillsboro, told Port officials to consider scaling back on
acquiring 90 acres. The city, he said, hopes to expand industrial land north
of the airport and would like as much space possible. Alternative C also
calls for building the new 3,600-foot runway farther north of the airport,
which would require that Northwest Evergreen Road be moved. About 2,500 feet
of the road, which was last moved in 2001, would shift about 300 feet to the
north. 

Like package B, part of package C includes turning part of the fairgrounds
into parking and business space. Another C option includes pushing aircraft
parking space closer to the airfield and moving a series of new hangars
toward the north end of the airport. 

In the coming months, Port officials plan to refine the package, which may
include a combination of alternatives from the three packages. The project
committee will meet again in March.


 Do you have an opinion about this story?
Share it with other readers in our CAA Discussion Forums

http://www.californiaaviation.org/dcfp/dcboard.php


*****************************************

Current CAA news channel:


Fair Use Notice
This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of political, human rights, economic, democracy and social justice issues, etc. We believe this constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law. In accordance with Title 17 U.S.C. Section 107, the material on this site is distributed without profit to those who have expressed a prior interest in receiving the included information for research and educational purposes. For more information go to: http://www.law.cornell.edu/uscode/17/107.html. If you wish to use copyrighted material from this site for purposes of your own that go beyond 'fair use', you must obtain permission from the copyright owner. If you have any queries regarding this issue, please Email us at stepheni@cwnet.com