"Anchorage airport millions over construction budget"


 
Tuesday, March 25, 2003

Anchorage airport millions over construction budget
The Associated Press


ANCHORAGE, - A huge makeover project at the Ted Stevens Anchorage
International Airport is running $186 million over the original budget.

State transportation officials said they need authority to borrow more money
to finish the work. But some state lawmakers, who must approve new
borrowing, and local airlines, which ultimately would foot the bill, said
the project needs to be scaled back.

The project includes terminal, road and parking improvements. The
centerpiece is a new 447,000-square-foot Concourse C that will house nine
jet gates, a ticketing area, a baggage claim, a security screening hall,
offices and operations support space.

The construction originally was expected to cost $230 million, but the
estimated cost has risen to $416 million. The project also is about two
years behind schedule, according to Dave Eberle, the state Transportation
Department regional director who is in charge of the project.

The construction has been beset by cost overruns and delays since the start
in 1999. Contributing factors are a flawed design, a decision to start
construction before permits were in hand, an expansion of the project and
post-Sept. 11, 2001, security changes.

Originally slated to be completed and operating by last summer, completion
is now expected in May 2004. Construction of the concourse was delayed more
than a year after the Anchorage Building Department in spring 2000 refused
to permit most of its structural design over worries that it could collapse
in an earthquake.

That delay, which Eberle blamed on flaws in the original plans submitted by
Coffman Engineers, the firm hired by the state to design the building, added
about $33 million to the total cost of the concourse, he said.

"It's our position that the delay related to permitting ties back to some
fundamental design errors created on their part, which gave rise to all
these added costs," Eberle told the Anchorage Daily News.

The Transportation Department already had ordered some of the materials, and
some of the initial work had begun on the new concourse before the city had
issued the permits.

Will Veelman, a principal at Coffman in charge of the firm's Anchorage
operations, declined to comment.

Eberle also blamed much of the cost overrun on security-related redesigns
made after the 2001 terrorist attacks.

"Osama bin Laden is responsible for a good share of it," he said. The
Transportation Department estimates that $23 million of the added cost of
Concourse C is related to the increased security requirements.

Another $22 million was tacked on to the total cost of the concourse after
the planners added 90,000 square feet to its original layout.

The largest chunk of the overrun is $108 million for the reconstruction of
the airport's existing main terminal, most of which is related to seismic
upgrades and security measures, according to Eberle.

With about 57 percent of the total project complete, the Transportation
Department has spent about $175 million of the $259 million currently
available for the project.

About $233 million of that came from revenue bond sales and interest earned
on investing the bond proceeds before spending them. The remaining $26
million came from federal transportation programs.

Eberle said the Transportation Department will ask legislators for approval
to sell another $63 million in revenue bonds this year to cover part of the
growing costs.

While it is a state entity, the airport is self-funded by passenger, airline
and tenant fees.

The airport doesn't tap the state treasury to fund its operations, but some
lawmakers worry about the cost overruns. They're cautious about approving
more borrowing in light of the current financial situation in which many of
the airlines find themselves.

"This project is out of control," said Sen. Donald Olson, D-Nome. "Here
we've got a project that's over budget, behind schedule, and they're asking
for more money."

Olson was among several legislators at a joint Senate and House
Transportation Committee meeting this month during which Transportation
Department officials detailed the scope of cost overruns.

The idea of borrowing more money to cover the rising costs of the terminal
redevelopment project isn't sitting well with some of the airlines. As users
of the airport, they pay fees that repay the bonds.

Alaska Airlines, the airport's largest tenant, proposes that the state defer
other construction and reduce the scope of the terminal redevelopment
project until it gets a handle on the overruns.

"The main thing that we're hoping to see is the deferment of other capital
projects, and we're talking continually with the (Transportation Department)
about that," said Jack Walsh, a spokesman for the Seattle-based airline.

 Do you have an opinion about this story?
Share it with other readers in our CAA Discussion Forums

http://www.californiaaviation.org/dc/dcboard.php

*****************************************

Current CAA news channel:


Fair Use Notice
This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of political, human rights, economic, democracy and social justice issues, etc. We believe this constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law. In accordance with Title 17 U.S.C. Section 107, the material on this site is distributed without profit to those who have expressed a prior interest in receiving the included information for research and educational purposes. For more information go to: http://www.law.cornell.edu/uscode/17/107.html. If you wish to use copyrighted material from this site for purposes of your own that go beyond 'fair use', you must obtain permission from the copyright owner. If you have any queries regarding this issue, please Email us at stepheni@cwnet.com