"Delays Could Plague Hartsfield Airport Runway"


 
Thursday, February 13, 2003

Delays Could Plague Airport Runway
WXIA-TV, GA


Heavy rain that stalled the construction of a deep drainage system could
cause a delay in construction of a new runway at Hartsfield Atlanta
International Airport.

The Atlanta Journal-Constitution reports the company hired for the drainage
of the airport's fifth runway has done no work since its equipment was
flooded in December.

The newspaper says other contractors fear there could be a domino effect of
delays and cost increases for the rest of the runway project.

The deadline for the project is May 1.

 Do you have an opinion about this story?
Share it with other readers in our CAA Discussion Forums

http://www.californiaaviation.org/dc/dcboard.php

*****************************************

Current CAA news channel:


Fair Use Notice
This site contains copyrighted material the use of which has not always been specifically authorized by the copyright owner. We are making such material available in our efforts to advance understanding of political, human rights, economic, democracy and social justice issues, etc. We believe this constitutes a 'fair use' of any such copyrighted material as provided for in section 107 of the US Copyright Law. In accordance with Title 17 U.S.C. Section 107, the material on this site is distributed without profit to those who have expressed a prior interest in receiving the included information for research and educational purposes. For more information go to: http://www.law.cornell.edu/uscode/17/107.html. If you wish to use copyrighted material from this site for purposes of your own that go beyond 'fair use', you must obtain permission from the copyright owner. If you have any queries regarding this issue, please Email us at stepheni@cwnet.com